NEW QUESTION # 19
What is the appropriate fire rating requirements for an ITE space?

  • A. 1/2 hour
  • B. 2 hours
  • C. 3 hours
  • D. 1 hour

Answer: D


NEW QUESTION # 20
What is the NEBS GR-3028-CORE recommended operational temperature.

  • A. Up To140 Degrees Fahrenheit /60 Degrees Celsius
  • B. -20°F/-28° C minimum and up to a maximum of104 ° Fahrenheit/40° Celsius
  • C. -30°F to +110°F (-34°C to +43°C)
  • D. -25°F to +125°F (-32°C to +52°C)

Answer: B


NEW QUESTION # 21
What IBC occupancy category are data centers placed in?

  • A. Category 3
  • B. Category 4
  • C. Category5
  • D. category6

Answer: B


NEW QUESTION # 22
where should engineering offices be located?

  • A. adjacent to equipment rooms they support
  • B. inside computer room
  • C. in a separate building
  • D. far away from the data center

Answer: A


NEW QUESTION # 23
What is a possible downside to customer-owned maintenance holes?

  • A. poor aesthetic appearance around facility exterior
  • B. fire risk near data center property
  • C. susceptibility to theft or damage by unauthorized personnel
  • D. leaks leading to water infiltration into data center

Answer: D


NEW QUESTION # 24
What electrical service feed options are there for a data center?

  • A. Single Entrance/Single Pathway
  • B. All of the above
  • C. Single Entrance/Dual Pathway
  • D. Dual Entrance/Dual Pathway

Answer: B


NEW QUESTION # 25
According to NEB, what is the recommended rate of temperature change per hour in a data center?

  • A. 36 degrees
  • B. 63 degrees
  • C. 45 degrees
  • D. 54 degrees
  • E. 72 degrees

Answer: D


NEW QUESTION # 26
What is the Fourth Preference Regarding Utility Service?

  • A. Two balanced feeds with different voltages derived from a single distribution station
  • B. One circuit from one substation, separate paths
  • C. At least two circuits from one substation fed via alternative power grid
  • D. At least four circuits each from different distribution stations but fed via common feeders

Answer: B


NEW QUESTION # 27
What is the preferred location of the power distribution unit?

  • A. a service gallery outside the computer room, if the A H J and feeder distances allow
  • B. inside a ventilation duct
  • C. in an unused area of another floor
  • D. under each server rack

Answer: A


NEW QUESTION # 28
What specific power consumption should be used to measure PU E?

  • A. only that which directly supports the data center like electrical distribution and cooling equipment
  • B. Maximal consumption across all measured devices in a specified amount of time.
  • C. Proportion between IT subsystem's input vs output capacities over some period.
  • D. What can directly support operations without including power utilization How much energy a particular device utilizes per unit of time?

Answer: A


NEW QUESTION # 29
What is the high temperature that must be maintained in a data center according to TIA-942?

  • A. 85 degrees
  • B. 80 degrees
  • C. 75 degrees
  • D. 70 degrees
  • E. 77 degrees

Answer: E


NEW QUESTION # 30
Where should telecom cabling be routed under an access floor?

  • A. In the plenum space
  • B. Above the access floor
  • C. In the equipment room
  • D. In the office area
  • E. In the cold aisle

Answer: E


NEW QUESTION # 31
What is the recommended raised floor height, especially for high density needs and underfloor HVAC?

  • A. 30"
  • B. 24"
  • C. 36"
  • D. 42"

Answer: C


NEW QUESTION # 32
How is the slab and all below grade components prepared in new construction?

  • A. only with steel reinforcement bars
  • B. with waterproof vinyl tiles
  • C. using standard concrete mix without any additives
  • D. with a continuously sealed rubberized moisture barrier

Answer: D


NEW QUESTION # 33
where should printers be located

  • A. near equipment that has active air flow to cool them down
  • B. placed outdoor, away from building facilities
  • C. in a dedicated print room with dedicated air handling system
  • D. beside high traffic areas

Answer: C


NEW QUESTION # 34
What is the recommendation regarding row length?

  • A. Maximum twenty-five racks in each row only
  • B. None
  • C. Ten Racks in Length
  • D. Do not exceed 20 racks in length and dead-end rows not to exceed ten racks long
  • E. All

Answer: D

Explanation:
Explanation:


NEW QUESTION # 35
What is the recommended floor loading capacity for a data center?

  • A. 1250 lbs per sq. ft.
  • B. 1750 lbs per sq. ft.
  • C. 1500 lbs per sq. ft.
  • D. 1000 lbs per sq. ft.
  • E. 2000 lbs per sq. ft.

Answer: C


NEW QUESTION # 36
Apart from marine cargo ports, hazardous material transport roadways, transportation roadways, and flight paths, what other things should a data centre be at least one mile away from?

  • A. Fireworks manufacturing companies only.
  • B. Petroleum storage installations like petrol stations & oil storage facilities only.
  • C. Waste-disposal units and dumpsites only.
  • D. All of The Above

Answer: D


NEW QUESTION # 37
How many air changes an hour inside an equipment room?

  • A. 1.50
  • B. 0.25
  • C. 2.00
  • D. 1.00
  • E. 0.50

Answer: B


NEW QUESTION # 38
What is the benefit to locating the power distribution unit supporting equipment outside the computer room

  • A. Allows for easier access by IT staff during maintenance tasks
  • B. None of the above
  • C. Enables greater energy efficiency
  • D. maintenance. activities are not taking place inside critical computer roomspace

Answer: D

Explanation:
Explanation:


NEW QUESTION # 39
What is recommended size ratio of Secure Storage Area?

  • A. 15-20% more than Computer Room's Cross Sectional Area
  • B. None Of These
  • C. 10% of Computer Room's Net Square Footage
  • D. 10% or greater than Available Floor Space
  • E. 5% of Computer Room Space

Answer: C


NEW QUESTION # 40
What is the appropriate fire rating requirements for a command center?

  • A. 1/2 hour
  • B. 2 hours
  • C. 3 hours
  • D. 1 hour

Answer: D